Working time and manpower for a commercial brewery
With a 100HL/Brew brewhouse, it can reach to 200,000HL annually by brewing 7 batches per day.For this large commercial brewery factory, usually it runs 18-24 hours per day to achieve high
economic benefit.
What’s more, working 24 hours has more advantages than 18 hours.
1) Much higher equipment utilization for 24 hours.
24 hours: brew 7-8 batch, 3 work shifts.
18 hours: brew 4-5 batch, 2 work shifts.
The difference is 3 batch.
.jpg)
2) Sanitation is easy to be controlled, and save cleaning workload.
Work 18 hours, stop 6 hours every day, it may germinate bacterium in pipeline or tanks inner
during stopping time.
So it is better to work continuously for several months, then stop 1-2 months to fix and maintain.
There is also a referenced manpower list.
| No. | Working Procedure | Numbers Of Staff | Shift |
| 1 | MALT TRANSFER | 3 | 3 work shifts |
| 2 | MILLING | 3 | 3 work shifts |
| 3 | BREWHOUSE | 6 | 3 work shifts |
| 4 | HEAT EXCHANGER COOLING | 3 | 3 work shifts |
| 5 | YEAST PROPAGATION | 1 | |
| 6 | FERMENTATION | 6 | 3 work shifts |
| 7 | FILER | 6 | 3 work shifts |
| 8 | BOTTLE LOADING | 3 | 1 work shift |
| 9 | BOTTLE WASHING | 2 | 1 work shift |
| 10 | BOTTLE CHECKING | 3 | 1 work shift |
| 11 | FILLING | 2 | 1 work shift |
| 12 | BEER TESTING AND CHECKING | 2 | 1 work shift |
| 13 | TUNNEL PASTEURIZER | 2 | 1 work shift |
| 14 | LABELING | 2 | 1 work shift |
| 15 | BEER TESTING AND CHECKING | 2 | 1 work shift |
| 16 | CASE PACKER | 2 | 1 work shift |
| 17 | OTHER | 6 | 1 work shift |